This SWMS covers plastering work using stilts and high-level access methods, from planning and equipment inspection through elevated work, sanding, cleanup and sign-off.

Activities covered include

  • Review the work scope and select an access method
  • Lift and install ceiling sheets
  • Dismount, clean, demobilise and sign off

Download immediately

Your editable Word and PDF files are ready to download after purchase.

Acceptance guaranteed

If your client or principal requests changes during document review, BlueSafe will help revise the document at no extra cost and support resubmission until it is accepted.

Plastering Stilts and High Level Access SWMS
  • 100% Compliant with Australian WHS Acts & Regulations
  • Fully Editable MS Word & PDF Formats Included
  • Pre-filled Content - Ready to Deploy Immediately
  • Customisable - Easily Add Your Logo & Site Details
  • Includes 2 Years of Free Compliance Updates

Product Overview

This SWMS covers plastering work using stilts and high-level access methods, from planning and equipment inspection through elevated work, sanding, cleanup and sign-off. It supports planning for falls, falling objects, access equipment, dust, electrical and manual-handling hazards.

Activities & Specific Tasks Covered

This document includes task-specific risk controls for:

  • Review the work scope and select an access method
  • Set up the work area and inspect access equipment
  • Erect scaffolds or platforms where required
  • Mount, adjust and use stilts for plastering
  • Position and operate elevated work platforms
  • Lift and install ceiling sheets
  • Complete high-level repairs
  • Tape and spot high joints
  • Sand surfaces and control dust
  • Dismount, clean, demobilise and sign off

Who is this for?

Suitable for contractors, workers, supervisors and businesses carrying out plastering with stilts and high-level access.

Specific Job Steps & Hazards Covered

Job Step / Activity Potential Hazards
Review scope and access method
  • Fall from high-level work
  • Unsuitable access equipment
  • Unplanned work changes
  • Worker inexperience
Set up work area
  • Unauthorised entry
  • Slips and trips
  • Falling objects
  • Poor lighting
  • Concealed services
Inspect access equipment
  • Equipment failure
  • Fall from defective platform
  • Unexpected EWP movement
  • Electrical shock from tools
Erect scaffold or platform
  • Fall during erection
  • Scaffold collapse
  • Falling components
  • Manual handling strain
Mount and adjust stilts
  • Fall while mounting
  • Stilt instability
  • Ankle and knee injury
  • Incorrect stilt adjustment
Use stilts for plastering
  • Fall from stilts
  • Trip over materials
  • Musculoskeletal strain
  • Dropped hand tools
  • Collision with obstruction
Position and operate EWP
  • EWP overturn
  • Fall from basket
  • Crush against ceiling
  • Plant collision
  • Falling tools
Lift and install ceiling sheets
  • Crush from falling sheet
  • Manual handling strain
  • Fall from access platform
  • Sheet lifter failure
  • Concealed service strike
Complete high-level repairs
  • Falling debris
  • Unstable ceiling lining
  • Silica and plaster dust
  • Overhead tool use
  • Electrical contact
Tape and spot high joints
  • Fall from height
  • Over-reaching
  • Repetitive strain
  • Compound splash
  • Dropped tools
Sand and control dust
  • Respirable crystalline silica
  • Plaster dust inhalation
  • Eye injury
  • Noise
  • Slips from dust accumulation
Dismount and clean area
  • Fall during dismount
  • Trip hazards
  • Manual handling strain
  • Exposure to dust
  • Unauthorised scaffold use
Demobilise and sign off
  • Plant movement
  • Unsecured equipment
  • Residual fall hazards
  • Incomplete repairs
  • Poor incident response

Need to add specific site requirements?

Use the BlueSafe Portal to tailor this SWMS with site-specific details, job steps, hazards, controls and responsibilities before work starts.

Acceptance Guaranteed: If your client or principal requests changes during document review, BlueSafe will help revise the document at no extra cost and support resubmission until it is accepted.

Legislation & References

The template includes references relevant to the documented work, including:

  • Applicable Commonwealth, state or territory WHS/OHS legislation and regulations, including duties to eliminate or minimise risks so far as is reasonably practicable, consult workers, provide safe plant, training, supervision and safe access.
  • Model Code of Practice: Managing the Risk of Falls at Workplaces, as adopted or approved in the relevant jurisdiction; use ground-level work or a solid construction first, then fall-prevention, work-positioning or fall-arrest controls.
  • Model Code of Practice: Construction Work, as adopted or approved in the relevant jurisdiction; prepare and comply with a SWMS where construction work involves a risk of a person falling more than 2 m, and maintain suitable lighting and housekeeping.
  • Model Code of Practice: How to Manage Work Health and Safety Risks, as adopted or approved in the relevant jurisdiction.
  • Model Code of Practice: Hazardous Manual Tasks, as adopted or approved in the relevant jurisdiction.
  • Model Code of Practice: Managing Risks of Hazardous Chemicals in the Workplace and Preparation of Safety Data Sheets for Hazardous Chemicals, as adopted or approved in the relevant jurisdiction.
  • AS/NZS 1576 series Scaffolding; AS/NZS 4576 Guidelines for scaffolding; AS 2550.10 Cranes, hoists and winches—Safe use—Mobile elevating work platforms; AS/NZS 1891.4 Personal equipment for work at height; AS/NZS 1715 and AS/NZS 1716 respiratory protection; AS/NZS 1337.1 eye protection; AS/NZS 2210.3 safety footwear; AS/NZS 4602.1 high-visibility garments; AS/NZS 3012 electrical installations—Construction and demolition sites.
  • Model WHS laws and model Codes are guidance only unless adopted, approved or otherwise given effect in the relevant jurisdiction.

Standard SWMS Features (Click to Expand)
  • Task-specific job steps, hazards and control measures
  • Initial and residual risk ratings
  • Assigned responsible persons for each job step
  • Plant, equipment and PPE requirements where applicable
  • Permits, qualifications and high-risk construction work details where applicable